Al-Makura begins probe of predecessors who ‘defrauded’ Nasarawa

Umaru Al-Makura, Nasarawa state governor, has set up a 10-man committee to investigate the abandonment of the N5.4 billion Farin-Ruwa Independent Power Plant project.

The hydro-electricity power project was awarded in May 2004 by senator Abdullahi Adamu, a former Nasarawa governor.

The initial project cost was put at N5.4 billion with a completion period of 36 months.

The project, whose execution cost was reviewed upward by Adamu’s successor, Aliyu Doma, has since been abandoned.

Advertisement

Mohammed Abdullahi, secretary to the state government, in a statement on Wednesday, said the committee will be chaired by Ayuba Ayenajeh, commissioner of finance and economic planning.

He said the committee will also review the Zimbabwean farmers’ project in Panda, Karu local government, and the concession agreement in respect of all state-owned hotels.

Abdullahi listed the affected hotels to include the New Keffi Hotel, NIPDC Conference Hotel, Lafia, and the Keffi Club.

Advertisement

He said: “The committee is also expected to investigate the role of key government officials in the agreements and ascertain where the state was short-changed.

“More particularly, the committee must fish out government officials who aided, colluded and abetted the defrauding of Nasarawa state and recommend appropriate sanctions.

“It should also recommend ways to prosecute those involved and recover government funds from such actors.”